Marlynn Ct. Project: Sewer Line installation
New tiered water rates for Escondido effective 1 Jan
2007:
![]()
23 Jan 2007 - First meeting held. Initial
agenda:
12 Feb 2007 - Second meeting held. A general fund is agreed upon for funds collected toward sewer line survey and installation.
20 Feb 2007 - Funds currently being collected by Casey and Duane nlt 1 Mar 2007 deadline.
27 Feb 2007 - $5K deposited at this time.
05 Mar 2007- $12K deposited in street fund toward first installment. Good job everyone.
15 Mar 2007 -
All homes on Marlynn Ct have contributed to the initial installment. $13K in street fund, thanks Casey & Duane for coordination of this initial installment.Proposal Legal Description & Plat Work Order Agreement
| Excel Engineering |
| 6 Mar 07 |
| Met with |
| 1 Apr 07 |
| 1 May 07 |
| 1 Jun 07 |
| 1 Jul 07 |
| 1 Aug 07 |
| 1 Sep 07 |
| 1 Oct 07 |
![]()
![]()
![]()
| Paperwork and permits required prior to installation |
| Begin installation process |
| Sewer Installation Timeline |